Poland’s Integrated Investment Plan (IIP) mechanism is proving a challenging route to securing development rights, with only around half of cases with specified outcomes resulting in plan adoption, according to research by real estate advisory firm Walter Herz.
The analysis examined more than 600 proceedings across 230 municipalities in all 16 Polish provinces. Approximately half remain ongoing. Of around 300 processed applications, 122 resulted in the adoption of an investment plan, 122 were closed without approval and 12 involved annulments of applications or previously adopted resolutions.
The duration of proceedings also presents a challenge for developers. An examination of 62 cases with documented submission and adoption dates found an average approval period of 273 days, equivalent to approximately nine months. Half took between 199 and 360 days, while individual cases ranged from 63 to 769 days.
Investors are required to finance the preparation of draft plans before submitting their applications, without any guarantee that municipal authorities will approve the proposed development. Municipal councils can refuse to initiate the procedure or withdraw their consent before an urban planning agreement is signed.
According to Katarzyna Tencza, Transaction Director at Walter Herz, preliminary discussions with local authorities can help investors assess the likelihood of approval before committing capital to the planning process.
Residential developments accounted for the largest category of applications, with 330 cases, followed by commercial and retail projects at 317. Tourism and leisure developments accounted for 89 proceedings, photovoltaic projects for 72 and warehouse and manufacturing developments for 55. Individual applications can cover multiple property uses.
Regional activity was highest in Małopolskie, with 121 proceedings, followed by Warmińsko-Mazurskie with 91 and Mazowieckie with 82. Pomorskie and Dolnośląskie recorded 55 and 48 cases, respectively.
Residential projects face requirements concerning compatibility with municipal planning policies and accessibility to public infrastructure, including schools and green spaces. Agreements associated with approved residential plans frequently require developers to finance or deliver roads, pavements, parking facilities and public transport infrastructure.
For commercial developments, the classification of land and the relationship between primary and complementary investments can determine whether projects qualify under the IIP framework. Walter Herz identifies particular limitations for retail parks, while large-scale retail developments exceeding 2,000 sqm of sales area require appropriate land-use designation.
Warehouse and manufacturing projects face additional challenges relating to road capacity, access for heavy goods vehicles and compatibility with designated industrial zones. Hotel, serviced apartment and senior living developments also require careful assessment of permitted property uses, as planning classifications can directly affect their operating and commercial models.
Renewable energy developments other than wind farms benefit from a simplified procedure, including a shorter public consultation period. However, land classification, infrastructure requirements and local authority positions remain relevant to project feasibility.
Bartłomiej Zagrodnik, Managing Partner and CEO of Walter Herz, emphasised the importance of distinguishing between the development potential outlined in an application and the rights formally established through an adopted plan.
For property investors, the findings highlight the importance of incorporating planning uncertainty, infrastructure obligations and approval timescales into land valuations and development budgets. The financial viability of a project may depend as much on the conditions negotiated with municipal authorities as on the development parameters themselves.
Source: Walter Herz, November 2026.